Integrity assessment of regulation system pipeline elements in hydroelectric generating set a6 of hydro power plant 'Djerdap 1'
(Society for Structural Integrity and Life, Institute for Material Testing, 2016)
Vertical Kaplan turbines with nominal power of 176 MW manufactured in Russia are installed in 6 hydroelectric generating sets at hydro power plant 'Djerdap 1' (Kladovo, Serbia). Most of the components are made of materials ...
Complex sulphide-barite ore leaching in ferric chloride solution
(Association of Metallurgical Engineers of Serbia, 2016)
The results of research on the leaching process of complex sulphide-barite ore were presented in this paper. The leaching process was carried out in a laboratory autoclave by ferric chloride solution. Considering that those ...